We need an attribute applied to "Cloned" projects where it respects the "lock" reports/projects. Let me explain the use case. A company set up a "Lock Report" rule for new projects. This is based on the project progress. Since a lot of the projects are similar, they like the clone feature, but if the user "forgets" to change the project status, it skips the workflow rules. Its almost like a clone project should be treated as a new project (with the first project status) versus simply a copy of the project.
Seth
complete
Done in v14. When you clone a project now the Status will default to the first Status in your list with State = "Open".